Tevatron June 2006 Startup Plan

 

This is a draft version of the startup plan for May 15 through June to commission beam in the Tevatron after the FEB to May shutdown.  The plan that is present is still under development.

 

Overview of Completed Work During Shutdown.

Startup Considerations:

Operational modes that Tevatron will startup:

 

 

 

 

 

Collider Startup Schedule

 

Tevatron Pre-Beam Plan and Schedule

·        Obtain and send out new DFG settings based on known magnet moves/unrolls  (Annala, Martens)

o       Jerry will send new settings only for 150 GeV.  We can copy the rest up later.

o       The B0 Low Beta DFGs are zeroed out at flattop and low beta.

o       The above changes are saved in C50 file ????.

Separator Polarity Switch checkout:

 

Verify all utilities are operational: vacuum, water, cryo.

 

 

 

 

style='margin-top:0in;margin-right:0in;margin-bottom:0in;margin-left:.5in; margin-bottom:.0001pt;text-indent:-.25in;line-height:150%;mso-list:l0 level1 lfo6; tab-stops:list .5in'>Do power supply checkout and ramping style='margin-top:0in;margin-right:0in;margin-bottom:0in;margin-left:1.0in; margin-bottom:.0001pt;text-indent:-.25in;line-height:150%;mso-list:l0 level2 lfo6; tab-stops:list 1.0in'> o       Ramp to 980 3 times, followed by a squeeze > 1 hr long.  <

o       Come back around, do a normal 20 min dry squeeze to prepare for injections.

o       Look for anomalous DFG behavior as result of new firmware via C23 compares.  (Readings should not change with the new firmware.)  We've already checked and corrected problems, but be vigilant in checking C23 compares.

 

 

Commission with Beam (# shifts needed is unsure 22 to 44)

 

Zero SQ and SQA0.

Zero H table dipoles at B0.

 

 

·         Establish circulating beam at 150 GeV  (Uncoalesced protons, central orbit)   2 shift

Run Mike Martens' BPM Test (group of commands in the "Proton Pilot" sequencer aggregate).  Note any bad BPM. 

Smooth 150 GeV orbit.  Use T39 profile file 660 for smoothing, which is a “separator off” profile.

 

Do aperture scans at A0, B0, D0 , E0, B48, A17  to rule out any major problems from shutdown work.  (Notify CDF and D0 before starting.  We don't want them to be surprised by SVX or SMT aborts.)

 

·         Additional 150 GeV work   3-4 shifts

 

·         1st Ramp/Flattop  (Uncoalesced protons, central orbit)    1 shift  (tune up chart)

 

·         Parse  1st Squeeze  (Uncoalesced protons, central orbit)    1 shifts

o        Set all B0 H table DFG's to zero.  Parse to low beta; smooth orbits, adjust tunes and coupling as a rough first pass to get beam to LB.

 

·         Work on Ramp (Uncoalesced protons, central orbit)    1 shifts

 

·         Work on Squeeze (Uncoalesced protons, central orbit)    1 shifts

·         Additional Work  up the Ramp & Squeeze (Uncoalesced protons, central orbit)    2 shifts


·         Tune-ups on the helices  (Uncoalesced protons)   9 shifts Total

    150Gev Tune up:  3 shifts

 

        Rough Idea of Plan

       

 

    Ramp/Flattop Tune up:  2 shifts

 

    Squeeze Tune up:  2 shifts

 

    Collisions Tune up: 1 shift

 

 

·         Prepare for HEP   2 to 3 shifts

 

 

 

 

 

 

·         Ready for HEP

o        Do a 36x36 store.

 

 

 

Security, Privacy, Legal

Updated June 08, 2006 RM